Gravity Line Down Murphy Road
Purpose
The Murphy Road segment of the Southeast Interceptor is the first
segment to be designed. As described in the City's Collection System Master
Plan, the Southeast Interceptor will “intercept” wastewater
flow that is currently routed through the City's downtown core
system, and route it around the south and east side of the City to a
connection with the existing Plant Interceptor pipeline in Northeast
Bend.
Schedule
The City has completed 60% design and preparation of construction bid
documents is expected to be complete by early Fall 2009. The project
is expected to be bid in Fall/Winter 2009/2010 and construction is expected
to begin in March 2010.
Design Details
Existing buried utility coordination
The City's design team has evaluated existing buried utilities
within the project areas and is closely coordinating with Roats Water
System and other franchise utilities within the City's right of
way to plan and accomplish the required utility relocations.
Geotechnical
Investigation
Citizens may have noticed the project team performing geotechnical borings
in September 2008 at locations along Murphy Road. This investigation
provided information to designers and will be provided to contractors
bidding the project. The boring logs confirmed the presence of rock at
relatively shallow depth and the project design and construction schedule
is expecting rock excavation, blasting, and use of rock hammers to accomplish
the required excavation.
Pipe plan and profile
This segment will be constructed from Parrell Road to Brosterhous Road
and will require deep excavations to allow existing pump stations to
be taken off-line and to provide future ability to provide sewer service
to existing and future development north and south of Murphy Road. Within
this segment the pipe diameter ranges from 18-inches to 24-inches and
is designed to be installed at depths of 9 to 23 feet below the existing
roadway. Trunk sewer line extensions will be extended within Parrell
Road, Tapadera, Benham, Broadmoor, Country Club Drive, and Brown Trout
Place.
Improvements to existing pump stations
The Southeast Interceptor solves immediate sewer service problems in
the area by disconnecting two of the City's existing sewer pump
stations (and many private home sumps) from a small 6-inch forcemain
(pressurized sewer pipe) and routes these flows by gravity to a single
large existing pump station. This will immediately reduce the City's
operation and maintenance costs associated with the pump stations (by
reducing equipment wear and long pump run times when pumps “compete” with
each other to pump flow down the forcemain) and reduce property owner
risk associated with failure of home sump components such as check valves.
Construction Phase Impacts
Traffic Control
The requirements to relocate existing utilities and to install
the interceptor at the required depths will require temporary detours around
the localized construction area. Only emergency traffic (fire, ambulance,
police) and local traffic (residents of properties accessed directly off
of Murphy Road) will be allowed to pass. The construction is expected to
take place in a “segment by segment” manner. Once pipeline
construction within a segment is complete, that section of road will be
reopened to normal traffic. This segmented approach will limit the length
of Murphy Road and connecting roads that are closed to normal traffic during
construction at any given time.
Detour Routes. The City's design team will define detour routes
as the project design advances, and the City's contractor will
be required to maintain temporary traffic control signage to direct drivers
to the selected routes. Preliminary work indicates that the shortest
detour route around the affected areas are acceptable. Local residents
can expect to see some increase in traffic on local streets adjacent
to Murphy Road as required to accommodate the detours.
Construction Duration,
Dates, and Hours of Construction
The City's design team estimates
that construction of the interceptor may occur at average production
rates of 40 feet of pipe installed per day along the deepest portions
of the alignment. At this production rates, work starting in March 2010
may continue for approximately 30 weeks (March 2010 through September
2010). The project team is refining the construction constraints to be
included in the bid package, but multiple crews, multiple construction
sites, and extended work hours may be allowed or required to reduce the
total construction duration. Additional information is expected to be
available as the project design progresses.
|